50 t hoist and T2T80 double-level rotating holding pole were used to erect the N4 crossing tower in the Yellow River crossing section of Haminan Zhengzhou ±800 kV UHVDC project, which could solve the difficulties of tower erection caused by tower's larger root distance, longer and heavier cross arm. The key technology of the N4 crossing tower erection was studied in detail, which could provide certain reference to the tower erection with long cross arm in UHVDC projects.
Key words: UHVDC power transmission, crossing tower, double-level rotating holding pole
BAI Junfeng,ZHAO Genbao,GUO Tianxing,ZHANG Hongtao. Key Technology of Crossing Tower Erection in the Yellow River Long-Span Section of Hazheng Transmission Line[J]. ELECTRIC POWER CONSTRUCTION, 2013, 34(8): 125-130.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.cepc.com.cn/EN/10.3969/j.issn.1000-7229.2013.08. 024
https://www.cepc.com.cn/EN/Y2013/V34/I8/125